TFT, Cribbs Causeway, Bristol Mall Nominees (1) and (2)

    Shell & Core adaption to existing unit including strip out, rooftop extension and new mezzanine floor and staircase in preparation for new Tenant Fit Out.

    • Project value: £326k
    • Project programme: 12 weeks

    Project Info

    Project Overview
    • Strip out existing shop (Unit 126), back to clear shell and isolation & relocation of services.
    • Erection of new steel framed extension with vertical cladding forming roof pop-up.
    • New roof constructed with insulated membrane on a metal deck.
    • Installation of ‘contractor designed’ temporary supports.
    • Removal of existing concrete roof slab.
    • Provision of new steel framed reinforced concrete mezzanine floor and staircase.
    • Reconfiguration of rooftop plant area including weathering.
    • Scheme was registered with Considerate Constructors Scheme.