Swan Shopping Centre, Eastleigh

    Formation of a new customer lift and stair core within the existing customer mall area

    • Project value: £600k
    • Project programme: 14 weeks

    Project Info

    Project Overview
    • Forming a customer lift and stair core serving three floors, two floors of retail mall and roof top car park
    • Partial demolition of existing vacant retail unit to create space for new lift and stair core
    • Demolition of existing lift and staircase
    • Forming new lift pit, lift shaft and staircase openings through existing structure
    • Formation of new steel framed roof top entrance lobby to serve car park
    • Works carried out with a mixture of day and night shifts to suit the operating requirements of the centre regarding noise and access
    • Works carried out in a live shopping centre environment behind branded customer facing hoardings