Complete design and construction of the landlords shell including full M&E services, fire alarm and intruder alarm. Works on site completed in 3 weeks.
Project Overview
- This project posed challenges relating to the Grade II listing of the store as well as the sensitive nature of the surrounding environment and close proximity of residential buildings.
- Close working on site with other contractors.
- Details, phased programming of works kept install time to a minimum.
- Pre-construction phasing with client representatives and other contractors.
- Liaison with tenants and sub-tenants on progress and program plans.