Sundorne Retail Park Shrewsbury

Remodelling of the existing store shop fronts, fascades, external canopy and a car park upgrade

  • Project value: £3.5m
  • Project programme: 6 months
  • Phase 1 – weeks 1 – 15
  • Phase 2a – weeks 9 – 20
  • Phase 2b – weeks 19 – 30
  • External Car Park Works – weeks 27 – 30

Project Info

Project Overview
  • The scheme at Sundorne comprises the removal of existing Portico entrances along with the glazed canopy, block paving and shop fronts. These are replaced with a new canopy, louvres and full height glazed shop fronts and new paved area.  Two of the stores are being sub divided during the alterations for new incoming tenants
  • The works are being phased behind a hoarded area with night working were necessary to alleviate any danger to the customers and staff
  • The schemes involve the installation of structural branded hoarding with segregated pedestrian zones, this allows safe access and ingress for the customers whilst the works are taking place
  • New exterior cladding along with a new structural steel canopy is being installed, the large anchor store being sub divided is having new roof cladding and the other units are having the roofs coated
  • All the units are having their existing shop fronts removed and replaced by new full height curtain walling, which include Phase 1 former Homebase Unit / Phase 2a former Staples, Carpet Right and Dream / Phase 2b DFS and External Car Park Works
  • Most of the site is a live environment and the stores will all remain trading whilst the remodelling takes place, structural tunnels have been designed for access to the stores